Projects Under Construction

C1. Street Rehabilitation - Phase 2 


Funded by: State Capital Outlay/ City Bond Issue

A. Scope of Work:
W. Arkansas St. - 7th St to 6th St - Reconstruction
E. Fertitta Blvd- 6th St to 5th St. - Reconstruction
Fertitta Blvd - 10th St. to 6th St. - Patch, cold plane and overlay

B. Estimated Cost:
Construction Cost:

Original Contract Amount -        $297,248.04
Current Contract Amount-         $297,248.04
Construction Cost To Date-       $293,267.05

Funding:
City Bond Issue -                      $297,248.04

C. Current Status:
Project has been accepted as Substantially Complete. 45 day lien period ends on September 2, 2017.

C2. Potable Water System Contract I- Hwy 28 Water Line Replacement at Ellis St.

Funded by: Drinking Water Revolving Loan Fund

A. Scope of Work:
Replace the 2" water line on the south side of LA 28 with an 8" line between LA 1213 and Elllis St.

B. Estimated Cost:

Construction Cost:
Original Contract Amount-  $61,479.10
Current Contract Amount-  $61,479.10
Construction Cost-To-Date $47,924.05

Funding:
DWRLF Grant $14,800.00
DWRLF Loan- $59,200.00
Total Project Cost- $74,000.00

C. Current Status:
Project has been accepted as Substantially Complete. 45 day lien period ends July 20, 2017.